The mobile recycling plant can handle masses that previously could not be reused. With a maximum capacity of 200 tonnes per hour, the plant is a unique facility with a high production capacity for stabilizing clay soils and other unstable masses.
Read more in the press release: PreZero first with unique clay and soil stabilization plant from Norditek
PreZero will be the first in Sweden with plants. "After a careful process of scanning the alternatives on the market, there was finally only Norditek left who can now solve this with a soil stabilization that provides both the right properties on the ground and can maintain a sufficiently high production capacity without the plant becoming a big monster," says Andreas Pettersson, Norditek.
As the recycling plant is mobile, PreZero can now offer on-site stabilization and reduce transport with negative environmental impact. As it will also be possible to use residual products such as burnt lime or ash in the stabilization process itself, it means that you now get a higher resource efficiency on other materials as well.
PreZero themselves tell us in their press release:
"We are constantly on the lookout and want to be at the forefront of new technological solutions so that we can offer our customers modern and efficient resource management," says Erik Karlstrand, project manager for the soil stabilization project and head of NA construction & infrastructure at PreZero.
The mobile recycling plant for soil stabilization will be commissioned in early 2025.